Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Thursday, 8 March 2012

Week 4 (Friday, Mar 9 - Thursday, Mar 15)

The planning has changed. Our new plan now is-
1- owner to remove fill
2- plumber to dig tanks, owner to remove fill on same day, tank install (1-2 days)
3- back filling of tanks (1 day)
4- laser grade site (1day)
5- pier holes to site followed by slab install (7 working days)

No comments:

Post a Comment