1) Planning
* Friday Mar 30: form-work with steel and waffle pods (part 1)
* Sat Mar 31: form-work with steel and waffle pods (part 2 to complete)
* Mon Apr 2: slab
* Tue-Wed Apr 3-4: retaining wall
* Thurs Apr 5: frame delivery
2) Jobs couldn't be done on the schedule:
* Internal plumb was on Mon Mar 25 while it was scheduled on Tue Mar 26
* Formwork with steel and waffle pods were scheduled on Wed and Thur Mar 28-29 but postponed on the following days due to the contractors' new job
Pictures update
Dirt mountain was removed and timber work + internal pipes were done
On Mar 27, Steels were laid outside the site which is not right location for our construction materials