Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Tuesday 17 April 2012

Week 9 (Tue, Apr 17 - Mon, Apr 23): Wet frame is crying

1) Summary of what had happened on Week 8

- as previous posted, external plumb was completed within 1 day on Tue Apr 10 (W8 D1)
- there were a series of deliveries


Blue steel beam was delivered  on Wed Apr 11 (W8 D2)


Another part of frame was arrived on Fri Apr 13 (W8 D4)

* SS advised frame was commenced on Mon Apr 16 (W8 D6), but no one was coming as I had a meeting with SS

* I had a very good talks with SS. Hopefully, he will deliver what we have discussed

* jobs for me in this week:
+ meeting with a new Kitchen guy to discuss about our pantry width in the kitchen
+ retaining wall
+ letter in respond to lovely neighbors


2) The team of 5 guys were on the site before 7 am

However, nature mother did not let them work today. And our frame all suffered very heavy rain.

Tomorrow, the weather seems still raining. Actually, I'm not worries about the delay but more concern with mould issue if rain still continue for several more days.

Try to stay positive and pray for strong and healthy frame.