Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Tuesday 5 June 2012

Week 16 (Tue Jun 5- Tue Jun 12): complete bricks?

1) Review week 15

- Brickies recommenced their job on time but the number of brickies were much less than expectation due to their own planning. Bad luck on us in this regards.

- There were only 3 brickies on last Wed, Thur and Fri . It meant there was only half of the team working for us.
- Mon Jun 4 was sunshine but there were none brickies working onsite

- On the second week with brickies, we were unfortunate to have only half of the team and wasted 1 day

2) Pictures times:


Front window bricks on the Day 3 (first week). Brickies did beautiful job!

Wall looks neat and bold!

 
Alfresco's very nice wall (on the Day 3_first bricking week)


Another high quality brick laying on the corner of Courtyard (on the Day 3 of the first bricking week)


Bricks' color on our garage wall is not too bad but the color is not quite uniformed! (On the Day 4 of the first bricking week)


Another high quality job done on our Courtyard's all  (On the Day 4 of the first bricking week)


Over the past 3 days of the second week, brickies did a bit on the front (as they mainly worked  on the house sides). However, their job quality is always on the first ranking. Happy happy


On the third day, there was only 4 brickies (only 3 brickies on the first two days)


On the storm day (Jun 5) there was 7 brickies on site

3) Schedules:

# Bricks to be done
# Facia and Gutter to be done

@ Tue Jun 5 had a storm so that building duration will be added up to 13 days


***** Jobs to chase up:
# Kitchen with bench island's width and the distance between cupboards
# Electrical layout
# Robes to Retreat

No comments:

Post a Comment