Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Thursday, 31 May 2012

Week 15 (May 29 Tue_ Jun 4 Mon): still bricking

1) Review week 14

+ All jobs done on the schedule
+ Surprised for scaffolding installation. It had done by 3 guys on the full two days (last Wed and Thursday), but it is needed to be fix more!
+ Thursday (May 24) rain so that the total building duration will be plus 12 days

2) Schedules
- bricks can't be completed on next Tuesday as there is only 3 guys working on Wed and Thursday due to other guys could not complete other jobs on Wed
- piles on the first floor
- carpenter will be back to install balcony
- termite guy will complete the job 
- facia and gutter have been booked on the next week (after bricks done) 

3) Jobs to chase up:

-  island bench's width and the distance between cupboard in the new kitchen layout
- gas points 
- robes
-  electrical plan

4 comments:

  1. Hi Kiki,
    Looking forward for photos!! :)

    We are in the same stage now.
    When are you going to get roof done ?

    M

    ReplyDelete
    Replies
    1. Hello M.

      Finally, I managed to post photos :)

      I don't think we are in the same stage as we need to have 6 brickies for 3-4 days. But I'm will be very happy if Fowler makes us just right behind you :).

      I guess it will be very lucky if we can have "hat" by the next weekend.

      Delete
  2. Hey Kiki,
    just wondering if Fowler notify you of raindays?

    Tina

    ReplyDelete
    Replies
    1. Hey Tina,

      No, Fowler don't notify me of rain days. I just want to count wet days to help myself stay positive and find out more justification during our long building :)

      Delete