Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Tuesday 6 March 2012

Sumary of what has happened and rain days since our site start on Friday, Feb 17

Week 1 (Fri, Feb 17 ~ Thur, Feb 24)

Weather: all six days were good for construction
Action: site fence, small rock delivery, peg-out.
Plus: we were really happy with SS, he always responded to our request within hours. 
Minus: a real action on the site was still away!

Week 2 (Fri, Feb 24 ~ Thur, Mar 1) 
Weather: Feb 24, 25, 27 and 28 were good
              Feb 29, Mar 1 were rain ==> plus 2 days on build duration
Action: excavation
Plus: we suffered a re-schedule on excavation, but it was still within planning
Minus: the weather (Feb 28) was just perfect but we couldn't do piers which was booked a week ago. What was a waste our 1 valuable dry day!

Week3( Fri, Mar 2 ~ Thur, Mar 8)
Weather: Mar 2, 3 and 8 were rain  ==> adding so far  5 days on build duration
               Mar 5, 6 and 7 were good
Action: nothing

No comments:

Post a Comment