Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Sunday 18 March 2012

Week 5 (Friday, Mar 16_ Thursday, Mar 22)

W5_D1_Friday Mar 16

We did complete the water tanks job as on the schedule.




So, we now feel a bit relax about water tank issue. I'm very much impressed about the Plumber, he is reliable and professional. Hope that Fowler have many contractors like their Plumber.

W 5_ D2_ Sat, Mar 17

It was raining_ Adding so far 6 days on building duration

Roughly, the plan for the remaining of Week 5 


1) Mon, Mar 19 : get the date for light excavation. Hopefully, it will be on the next day or next 2 days
2) Thursday- Friday, Mar 22-23: build the retaining wall 

My check list:
1) confirm the plan for piers and plumbing and other preparations for slab which is supposed for 8 dry working days.
2) confirm with SS about re-organize the wet area
3) confirm with SS about cold water tap behind Fridge space
4) inform SS about the schedule for retaining wall building 


No comments:

Post a Comment