Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Thursday 29 March 2012

Week 7 (Friday Mar 30 __Thursday Apr 5)

1) Planning

* Friday Mar 30: form-work with steel and waffle pods (part 1)
* Sat Mar 31: form-work with steel and waffle pods (part 2 to complete)
* Mon Apr 2: slab
* Tue-Wed Apr 3-4: retaining wall
* Thurs Apr 5: frame delivery

2) Jobs couldn't be done on the schedule:

* Internal plumb was on Mon Mar 25 while it was scheduled on Tue Mar 26
* Formwork with steel and waffle pods were scheduled on Wed and Thur Mar 28-29 but postponed on the following days  due to the contractors' new job

* It rained on Wed Mar 28 adding 8 days on the building duration

Pictures update
Dirt mountain was removed and timber work + internal pipes were done

On Mar 27, Steels were laid outside the site which is not right location for our construction materials

No comments:

Post a Comment