Our rebuild modified Vienna 42 with Fowler

Our rebuild modified Vienna 42 with Fowler
OUR REBUILD MODIFIED VIENNA 42 with FOWLER

Sunday 25 March 2012

Week 6 (Fri, Mar 23 - Thurs, Mar 29)

1) Completed piering and digging Drop Edge Beam

2) Timber formwork will be on Monday, Mar 26.

* Need to catch up with SS to confirm for H-class slab, dirt removal date and internal plumbing date

* I hope the site will be drier than last Fri, Mar 23 though we had two light showers on Sun, Mar 25

3) Internal plumbing
I really hope SS will re-organize the wet area for us. We won't have a drama here.

4) Arrange still and waffle pods

5) Slab
We hope we will have a slab before it rain again.

Other notes for Week 7
* Frame delivery will be on Thurs Apr 5
* Retaining wall building will be on Tue Apr 3-Wed Apr 4

** Mon Mar 19 was rain hence adding so far 7 days on the build duration

No comments:

Post a Comment